Greenland’s Terms for Hydropower
Bidders will face security screening, and the government will weigh whether Greenlanders can commute to the jobs they create.

AI-generated photo illustration.
Greenland opened prequalification on November 24 for development of Tasersiaq and Tarsartuup Tasersua, two hydropower sites between Kangerlussuaq and Nuuk. The project documents estimate a combined installed capacity of around 1,100 megawatts and annual production of about 9,600 gigawatt-hours. The application deadline is May 1, 2027.
The power projects are tied to industrial development. The procurement requires at least one industrial project to use the electricity. Applicants must demonstrate their financial and technical capacity and meet requirements on sanctions, public safety and national security. The rules also apply to consortium members and other entities whose resources an applicant relies on.
Who gets the return
The government, Naalakkersuisut, wants a resource payment linked to each unit of electricity produced, together with public co-ownership through preferred shares that require no upfront capital contribution from Greenland. The model applies to the power plants. The industries that would buy the electricity are outside that ownership arrangement.
The choice of where those industries operate will also count. Naalakkersuisut says it will favor proposals that create opportunities near inhabited areas, where Greenlanders can reach work through a daily commute. The government drew up the criteria after public meetings and discussions with Qeqqata Municipality.
Screening before award
The government delayed the process in October to adjust the tender material in light of the new Greenland defense agreement, according to Sermitsiaq, a Greenlandic newspaper. The agreement contains investment provisions for sensitive sectors, including critical infrastructure. The project documents provide for screening during prequalification and again at the tender stage.
Greenland expects to determine in 2027 which groups qualify to compete. That stage will establish who can submit a final offer on the plants, the industrial customer and the financial terms for the public.